Let us discuss how to calculate the Man Day cost. MD refers Man Day; it is a unit of measurement for workforce.
Eight-Hour working is called One shift and one person working one shift (8 Hours) is called one man day.
If the work gang comprises 10 workmen and working one shift is equal to 10 MD and if the gang works 6 days then it is 60MD.
In construction industry over time has existed. It is subject to the nature of job. Normally 3 Hours overtime is regular in all sites. However, benefits will not be applicable on overtime wages.
During MD rate calculations terminal benefits are subject to the duration and local site environment
MD rate arrives from
PF & Admin. Charges of employer portion
There are several laws in India which govern the maximum overtime hours allowed in India and also provide for an overtime calculation formula in India. Based on the industry one works for; the overtime payment rules vary. Some workplaces may be governed by the central laws while the other might be a subject of state laws.